CRW Run
Use the selected Linear project as the planning source and keep this Codex task as its coordinator: one parent per project, one child per issue. Follow the shared parent and child scope, including standalone issues and explicit current-task work. Each child owns its checkout and execution; this task owns scope, dependencies, dispatch receipts, review, and the decision to release the next work.
Run owns project execution, including newly ready successors within the agreed scope.
crw-loop adds a separately requested parent goal and host-driven
continuation to that same execution; it does not enlarge Run's project scope.
Load the installed codexclaw:cxc-dev and relevant surface skills for development
and review work. A child whose effective workflow is CXC Loop loads the installed
codexclaw:cxc-loop and codexclaw:cxc-pabcd and owns its goal, goalplan and phases.
Resolve current installed paths; never copy plugin versions from old records.
CXC owns those phases and subagent routing; the parent does not adopt a child's FSM.
Read Integrations for Linear document
authority, tools, and Paperthin invocation rules. Use the available Linear tools
and relevant workspace Agent Skills for full documents, criteria, and work records.
Use readchk for bundled scope or model corrections, and catchup when the user
needs a refreshed briefing. Route roadmap authoring to
crw-plan within the user's requested scope.
Determine the requested operation
A submitted $crw-run <Linear project link> execution request designates or restores
this task as the fixed parent using Project parent binding
and executes the agreed project scope. Record that scope and delivery boundary,
including its known blocked successors, rather than equating scope with today's ready
batch. Reconcile existing work, reuse/create responsible children, verify and integrate
their results, and admit newly ready in-scope issues as capacity opens. The first batch
is a scheduling choice, not a finish boundary. The link does not approve undefined work,
future backlog additions, another project's work or replacing another parent.
An explicit request for a parent goal or unattended host continuation routes to
crw-loop. Ordinary requests to finish the project or continue its next issue remain
Run execution; they do not themselves create a goal. Inside an authorized Loop, Run
returns progress and pending obligations to the same Loop owner without creating
another goal. Existing scope and authorization survive skill routing.
Explicit status, explanation, plan-only, batch, issue, no-create, no-goal, no-merge, or current-task limits override the default. An issue or milestone target stays within that scope; it is not a request to run its whole project. A quoted example, a question about usage, automatic skill selection, or an unsubmitted UI prompt does not activate this shorthand. Host and tool restrictions still govern each action, including task creation and goal activation.
- Plan/prompts: inspect project state and prepare task packets; do not launch.
- Bind/restore only: apply Project parent binding and report the connection; do not dispatch children or create a goal.
- Dispatch a named batch: reuse prior authorization and settings, refresh its prerequisites, then launch only that batch.
- Run a project or milestone: carry its agreed scope through delivery, including successors. A milestone, named batch or issue narrows the same project's assignment. Parent goal creation and host-driven continuation belong to an authorized Loop.
- Status only: read existing tasks and evidence without waking them.
- Verify completed work: inspect its exact revision and relevant behavior, send in-scope corrections to the existing responsible task, and recheck its delivery under the established assignment. Respect explicit report-only limits.
A named-model correction steers the current dispatch; it does not authorize global model or CXC role-config changes. Preserve explicit model and effort per task; take an unchosen model, effort, or workflow from Default independent execution. Do not copy a model choice from a previous project into a new one.
Resolve task-creation authority from the submitted operation above and the conversation below; never override host requirements. Apply the shared delivery and integration default and inherit existing authorization for coordination records and recovery. Release publication, deployment, issue closure, and unrelated messages need scope covering those actions. When the user designates this as the fixed management task, use Project parent binding for its recorded project link, title, and sidebar pin, then continue the authorized execution here.
Keep a project run moving
Run does not initialize, resume, complete or block a parent goal. It keeps progressing the agreed project scope during execution: dispatch, wait, verify, correct, integrate and start eligible successors. Before any child dispatch, record its observation path and the requested delivery boundary under OPS-8.1.
A dispatch-only request may return with pending ownership and an exact next step. Otherwise continue until the agreed scope is delivered, the user stops, a resource limit is reached, or no authorized progress is possible. An empty ready queue while children run calls for bounded observation; a blocked issue does not stop independent work. If the host ends the turn, preserve the unfinished project and exact resume step, not a claim that the first batch completed the request. Run alone promises no automatic future wake-up. A status-only request wakes nothing.
For authorized automatic continuation, crw-loop owns the parent host goal and automatic continuation across turns. Returning from Run hands control back to that same owner. Explicit pause/no-goal limits still win, and existing CXC parent state must be reconciled through its supported lifecycle, never reset to avoid a guard. The default absence of a Run parent goal does not alter child CXC defaults.
Independent implementation tasks
In this managed execution workflow, implementation belongs to a responsible independent child Codex task, including a single issue, an existing worktree, and repairs to an existing PR. The coordinator owns scope selection, preparation, dispatch, delivery validation, and authorized integration; a child whose assignment covers publication owns its own pull request, including its checks and its review cycle. Issue count and checkout availability do not turn the coordinator into the implementation worker.
Read the coordination record and inspect the existing responsible task and any current writer before creating or assigning work. Verify its actual task/host ID, issue scope, current turn, checkout ownership, and execution settings. Reuse that task for compatible follow-up work on the same issue under the existing assignment. A busy task, an uncertain send, or an inaccessible record is not evidence that no writer exists; reconcile before retrying or considering a replacement.
Where a relay holds the assignment, ask it first: an assignment lookup by issue returns the existing relationship, its responsible child, its current state, and the next expected action. Registering a different child for an issue that already has an active or paused assignment is refused in the same transaction that would have recorded it, so duplicate registered ownership cannot be created even by two concurrent attempts.
That is a guarantee about the assignment RECORD, and it is not a lock taken before
creation: registration needs the task id creation returns, so two coordinators can
both find an issue unassigned and both create a child before either registers. The
lookup makes reuse the first move and names an existing owner; the registration
transaction is what settles which child owns the issue. A coordinator refused with
duplicate_assignment has therefore just created a losing writer. Assign it nothing
further, and tell it to stand down and preserve its artifact without waiting for it to
go idle: read its status and active turn, steer that exact turn with the stand-down
instruction, and use the ordinary message path only if it is already idle. Then
reconcile that artifact with the owner the refusal named. The bridge withholds an
interrupt, so nothing here stops its turn; a delivered instruction is not a stop, its
writes stay unreviewed until reconciled, and stopping it is never described as
something already done. Commands are in
codex-session-relay, transport limits in
codex-thread-bridge.
Internal subagents are bounded helpers within their owning task. A child may use them for its implementation; the coordinator may use them for bounded inspection or review. A subagent handle, even one represented as a thread ID, is not evidence of an independent child task. Do not replace the child with parent implementation or a parent-owned implementation subagent just because the issue is small or a creation path is unavailable.
Resolve creation and execution intent from the full conversation for this scope, including prior authorization and the plan the user is accepting. Explicit intent does not require a particular word such as “create” or “생성”. Accepting a concrete new-task plan requests its execution; clear delegation in an established independent-task workflow carries that task intent. Preserve the referenced project, task/batch/run scope, and settings without asking the user to restate them. Higher-priority host/tool restrictions still apply.
| Invocation context | Action |
|---|---|
Submitted $crw-run <Linear project link> execution request with no narrower operation |
Bind/restore the fixed parent and execute the agreed project scope, including successors, without creating a parent goal; host restrictions still apply |
| Request to create/reuse child tasks, a submitted prompt expressing that intent, or clear project delegation after independent tasks were established as the execution workflow | Reuse the responsible task first; create only when needed within that scope and allowed by the host, without another authorization round |
| Concrete new-task plan followed by the user's acceptance, such as “진행해” or “응” | Execute the accepted plan within its stated scope; do not ask for a creation keyword |
| Resume of an authorized run, including after compaction | Recover its authorization source, scope, and settings; refresh ownership and prerequisites, then continue the remaining in-scope obligations, including successors. Preserve an explicitly batch-limited assignment; do not repeat approval already covering the scope |
Standalone short invocation such as $crw-run 다음 작업 진행해줘, with genuinely no creation intent in the conversation or prior authorization for this scope |
Prepare the issue packet and inspect ownership; if a new task is needed and the host requires an explicit creation request, obtain only that missing request |
Merely mentioning the skill's name, an unsubmitted UI default prompt, a quoted example, or task designation without execution is not a child-creation request. The submitted project-run shorthand above is an execution request. Permission for an unrelated earlier task does not authorize this scope. Discover a permitted tool; a different transport does not waive the host's creation rule. If authority or capability is missing, finish the executable packet and baseline preparation, report the specific missing permission or tool, and request only the unresolved decision. Do not silently switch execution mode or widen permissions.
An explicit request to implement within the current task overrides this workflow's default separation: honor it with CXC and label the actual mode accurately. Status-only, report-only, read-only, and no-create limits also win. Ordinary coordinator review, verification, CI inspection, and authorized integration remain here. Assignment is not Loop evidence: creating or assigning a child task does not by itself create a goal or prove that a Loop started.
Establish the project baseline
Read the linked Linear project, canonical planning/decision documents, milestone descriptions, full issue criteria, and blocking relations through the available Linear connector. Inspect the repository's applicable guidance, branch, dirty state, worktrees, and relevant implementation. Refresh volatile claims before acting. A project's summary prose, milestone percentage, issue status, merged PR, and deployed behavior can disagree; record the discrepancy rather than silently treating them as equivalent. Missing connector access is a concrete limitation, not permission to invent issue details.
For a standalone issue, read that issue, its linked canonical documents and blocking relations directly; project and milestone reads are inapplicable. Keep its issue-scoped ownership and the existing management binding unchanged. Do not create a project or project-parent binding to satisfy this baseline. If a transport requires a project binding, use a permitted projectless execution path or report that capability gap; never invent a project ID for a receipt.
For repository-changing work, compare local and remote commit ancestry. Preserve local-only commits and dirty work. Record a full baseline commit for each task and decide how any prerequisite changes will reach it. Do not push shared baseline commits through every task.
At initial dispatch and after a completion, blocker, or integration, scan the agreed project scope for useful parallel work, including newly unblocked successors. An explicitly limited batch or issue remains limited in both Run and Loop. Check verified prerequisites, overlapping edit surfaces, existing writers, shared runtime resources, and available execution capacity. Dispatch the largest useful set of independent ready issues within explicit concurrency, budget, and host limits. A shared repository alone is not a reason to serialize; separate owned checkouts can carry independent changes.
Do not wait for an entire batch to finish before filling available capacity with
eligible independent work inside that boundary. Independent issue statuses alone do not establish
independence: serialize shared schema, persistence, contract, or central UI changes
when separation would cost more than it saves. Keep integration into a shared
target serial and recheck each candidate against the updated base. Record a
concrete dependency, conflict, ownership, or capacity reason for deferring an
otherwise ready issue. Do not invent extra issues or duplicate writers just to
increase concurrency; reconcile an oversized issue through crw-plan when a
useful split fits the authorized scope.
Apply the shared issue-to-PR mapping:
one implementation issue per PR, with one issue/PR pair per implementation
packet. A batch retains those separate pairs. If one issue needs several PRs,
or a proposed PR would deliver several issues, reconcile the plan through
crw-plan before new dispatch; preserve existing owners and active work.
Keep the human-readable coordination record in the project's linked Linear document as part of the management assignment, without a separate recording request. For a standalone issue, use its existing linked coordination document or a compact owned section in the issue within the authorized recording scope. Keep private recovery receipts keyed by the issue and actual task IDs; no project record or project-level parent binding is required. If delegation or a relay is used, retain the real coordinator task ID and routing identity; projectless does not mean coordinatorless. Preserve unrelated issue content on each update. For explicit read-only scope or unavailable access, return the unsynced update and retain the task's private recovery receipt. Keep raw launch receipts and sensitive evidence in an appropriate private location; local snapshots point to the Linear document and are not another planning source. Do not store project state or credentials inside this installed skill.
Before assigning a checkout, apply the shared repository resolution and put its verified issue target, remote, integration branch and full baseline in the packet. Reuse an existing task's worktree and issue branch on resume; classification changes alone never relocate it. Non-PR work can omit those code fields with its explicit result and verification instead.
Prepare and dispatch
Read Task packet when preparing prompts. Each packet must stand alone in a fresh context and name its prerequisites, scope, baseline, acceptance criteria, verification, and return artifacts. For non-PR work without repository changes, use the source document/data revision as the baseline and return both that input baseline and the verified output identity: a stable result link plus delivered revision/updated-at evidence, or a durable file locator plus its digest. Snapshot the verified output when the source cannot recover old revisions. Omit Git ancestry, worktree/branch/commit, push/PR/review/merge requirements and their OPS clauses when they do not apply; do not create a repository or empty PR. Keep task ownership, access, settings, criteria and recovery evidence. This non-PR path applies throughout dispatch, observation and completion below.
For repository-changing work, every packet carries the current delivery contract, and where the template's older delivery menu disagrees the contract wins. Name in the packet that the child owns its commits, push, the pull request and the review on that same pull request through to the applicable gates, and that the coordinator performs the merge while release and deployment remain the user's. Then give the child OPS-5.5 and OPS-9 from Operations contract as context of its own: cite them by id where the child can read this repository, and carry the clause text itself where it cannot, because a packet has to stand alone and a child that never sees OPS-9.1 and OPS-9.2 can follow the summary above while still requesting review on a draft or reporting a missing mandatory check as complete. Carry that text rather than a summary of it. A quotation can be diffed against its source and regenerated when the clause moves, while a paraphrase cannot, and it is the paraphrase that drifts unnoticed. Name the capability the child is being created with, and for a task that cannot write git metadata say so explicitly and assign the fallback, since those are the parts the contract cannot know. A packet carrying neither clause sends a child the previous workflow.
Apply Child task titles:
ISSUE-ID · short task name · workflow. Supply the title through the supported
creation field, verify the actual title by task ID, and correct it on the same
managed task when supported. The packet's title alone is not app-state evidence.
Apply Independent implementation tasks even when no new branch or worktree is needed. Non-PR work uses its permitted working directory and artifact access without Git metadata. For code work, reuse a checkout whose ownership is verified for the responsible child; a coordinator may prepare it before handoff. Otherwise follow the project/user placement convention. Record the actual path, branch, and owner; do not create a second checkout just to prove task separation. Placement, the ownership columns, and the write split between a coordinator that prepares git metadata and a child that only edits source are in Operations contract, which also owns the shared relay service, its durable store, and the parent's continuation and waiting mode.
Discover the live creation tool and schema before claiming availability.
Use native app task tools when suitable. Before proposing or adopting the official
managed worktree as the creation path, consult
Official worktree verification, because
a capability flag from another transport is not evidence about that path. Run its probe
only when the current scope authorizes the task creation, resume, writes and pushes it
performs; under a plan-only or no-create scope, reuse still-applicable evidence or
report the path as unverified rather than letting a proposal become live execution.
If using codex-thread-bridge, read
Bridge launch and recovery before any mutation.
If no usable creation tool exists, reuse a verified existing task when its
follow-up path and authorization suffice. Otherwise finish the packets and
preparation, identify the missing capability, and report that nothing was
launched; parent or internal-subagent implementation is not a substitute.
Apply the effective settings through the creation tool's real arguments, and send
the bounded issue packet in the initial work prompt so the child can start the
assigned work. When CXC Loop is the effective workflow, that prompt invokes the
installed cxc-loop skill; an explicit non-Loop or no-goal alternative omits that
invocation and names the agreed workflow instead. Verify the returned task ID,
cwd/workspace roots, model, effort, and full permission profile from the creation
receipt, and reconcile a mismatch on that same task. A prompt saying “use this
model” is not a configuration override. A catalog entry is not proof of the model
that served the request. Settle a setting the creation path cannot apply before
creating the task rather than downgrading it.
Record request ID, task ID, host ID when supplied, turn ID, requested/actual title and settings, and launch outcome. For code work include the checkout and full Git baseline SHA. For non-PR work include the permitted working location and input source revision; add the delivered output identity when the result exists. Do not put raw credentials or full private prompts in public project records.
The request ID and the task ID are not two names for one thing, and the record keeps both because they become available at different moments. The request ID is chosen BEFORE the creation call, so it is the one handle that already exists while the task does not; it is the management marker, it travels in the same full work request as the assignment, and it is what identifies this creation afterwards. The task ID is the native identity that reuse, registration and every later mutation route on, and it exists only once creation has actually returned it. Join the two from the creation receipt.
What to do when that receipt never arrived depends on the transport, so establish which one you are on before relying on either path. Where it accepts a caller-chosen id and exposes a lookup keyed on it, resolve the marker through that lookup rather than issuing a second creation under a new marker; Bridge launch and recovery is that mechanism here. Where it does not, and some permitted native creation tools do not, the marker is still worth recording for the coordination record but it is not a recovery key: an id that only travelled inside the prompt is indexed nowhere, and treating it as a handle leaves an uncertain creation filed forever as a writer nobody can find. There the backend's own task listing is where the search starts. Narrow it only on what the host cannot rewrite, which in practice is the workspace and a time window around the call. The title is a hint and never a filter: a host may generate or change it, so filtering on it can exclude the very task being looked for and leave a live writer orphaned, which is worse than a wide list. Narrowing is not identifying either way. These fields are non-unique, two tasks can share them, and adopting a candidate on that basis is how a coincident task gets registered or steered as somebody else's child. Bind it only on something that could not be true of another task, such as its own first user message being the packet that was dispatched, read from that task. Widen the search before concluding nothing is there, and where nothing is identified the creation stays unresolved and is reported as such; an unidentified candidate is not the child, and identity stays on stable IDs.
Neither path always settles. A response lost at the wrong moment leaves the outcome genuinely unresolved, and an unresolved outcome means a writer may exist. Treat it as one: create no replacement while it stands, and report it rather than overwrite it.
Where a relay holds the assignment, register the relationship with its authorized scope, record BOTH the parent's and the child's authorized execution settings from the actual creation receipts, and record the issue's criteria as the canonical set so the later verdict rules on the agreed obligations rather than on a reviewer's recollection. All of that reuses what creation and the issue already provide; none of it is a readiness round trip and none needs another approval. Registration uses the task id creation returns, so the packet carries the shared state directory and the exact issue identity registration was given instead, which depend on nothing creation returns; the child resolves its own relationship by issue lookup when it emits, which is after the work rather than at startup. That lookup matches the registered string exactly, so a display key in the packet where registration used a stable id resolves to nothing. A child fast enough to reach that lookup before registration lands finds nothing, reports its completion unemitted and preserves the artifact; recover it from that same task after registering, in a later turn carrying a continuation claim, rather than creating another child or writing on its behalf. The receipt it then emits is the same event the on-time one would have been. Field-level detail, including that recovery and which settings field is nested in the response, is in codex-session-relay. Without a relay this paragraph does not apply and the dispatch above stands as written.
When CXC Loop is the effective workflow, the child owns its goal, goalplan, and
phases through its own cxc-loop and cxc-pabcd; the coordinator checks the
resulting evidence, not the child's internals. Creating a task does not create a
goal; an active turn does not prove the loop is armed. Missing loop prerequisites
are reported explicitly, with no silent substitution of a different workflow.
Observe and verify
Use a compact native wait_threads snapshot with each task's actual host and
cursor, or the bridge's exact task/turn wait. Batch independent reads. A timeout
does not stop or complete work; it is not a reason to send the prompt again.
Observe the host's wait limits and keep the user informed without repeating
unchanged snapshots.
Describe evidence separately:
| Claim | Evidence required |
|---|---|
| Independent child assigned | Creation or reuse receipt from the independent-task interface, actual task/host ID and ownership; not an internal-subagent handle |
| New task created | Creation receipt and recoverable task ID; reuse is recorded separately |
| Prompt dispatched | Accepted turn ID and matching user message |
| Instruction delivered into a running turn | Accepted steer receipt naming the guarded turn ID; a refused or mismatched turn ID is not delivery |
| Peer read an instruction | The task's own transcript showing the steered input; an acceptance receipt does not establish it |
| Peer acted on an instruction | The changed work, revision or reply; neither acceptance nor a read establishes it |
| Goal paused | The goal read back as paused; it does not establish that a running turn stopped |
| Requested settings applied | Actual returned settings, not prompt text |
| CXC Loop active | Child's active goal and current goalplan/FSM evidence |
| Agreed workflow actually followed | That task's own recorded phases, plan and evidence for this assignment. A skill-loading line, an acceptance receipt, or the instruction quoted back is an indication of receipt, not of compliance |
| Child reused its own existing goal | That task's current goal and goalplan read back under its own identity. A second goal opened for the same assignment is a duplicate, not a resume |
| Work delivered | Completed turn plus actual commit/diff and checks for code; verified result with both input baseline and delivered output revision/digest for non-PR work |
| Pull request review handled by the child | Per-finding trail on that PR: the finding, the commit that addressed it, and the recheck |
| Child reports normal completion | Required checks and reviews finished on the current head, blocking findings resolved; a missing mandatory review or check is blocked, not complete |
| Verified for integration | Coordinator reviewed the exact revision and acceptance criteria |
| Receipt recorded, where a relay holds the assignment | The child's completion receipt with its revision hash and manifest |
| Verification decision, where a relay holds the assignment | A verdict at the current head revision, covering the registered criteria and naming the criteria set it was reviewed against |
| Coordination summary written | The coordinator's own connector write, confirmed by a readback carrying that job's structured record |
| Merged by the coordinator | Linear criteria and the PR's latest diff/base/head/checks/review resolution checked, then the actual landing verified |
| Release or deployment | The user's approval for that action, obtained before a merge known to trigger it |
Do not assume a worktree/task returned by a backend appears in the app's project. Check the Desktop listing separately when the user needs that association.
After non-PR delivery, verify the delivered output revision/digest against its input baseline and acceptance criteria. A later edit at the same URL invalidates reused verification; it is not the same output. No commit or merge is required. After code delivery, identify the final commit or frozen hashed diff/file bundle, then check the prerequisite ancestry, scoped diff, acceptance criteria, meaningful negative cases, and relevant user-visible behavior. Reuse valid proof for the same revision and criteria; run missing checks or checks invalidated by integration. A completed turn may contain a failure or interruption.
Where a relay holds the assignment, verify the revision it reports as current. If a
newer revision arrived while the review was in progress, the older result is not a
completion: re-read the current revision and verify that one. Two competing
revisions with no stated supersession are ambiguous, and an ambiguous head withholds
rather than picking whichever arrived later. If the criteria changed after a review,
that review certified wording nobody is judging by now, and there are two routes
back: judging the same revision again against the set now in force, or opening a
fresh execution generation. The same revision can be judged again only while it is
still the one the assignment stands on and any verdict it carries is verified;
a changed artifact, or an event already ruled needs_changes, unverified or
aborted, takes the new generation. See codex-session-relay.
Use independent review when scope/risk warrants it, through the current CXC subagent protocol inside the appropriate checkout. A worker's self-report alone does not fulfill independent verification.
For substantial intent or acceptance uncertainty, use
crw-check as a bounded audit and retain coordination
here. Use crw-logic for a specific suspected logical
violation and mandela for self-confirming evaluation evidence. Use shower when
a nontrivial task packet needs a fresh-reader check, and re0 to refresh that
packet after changes. Do not run every helper on every delivery or auto-invoke
Paperthin's user-only skills.
After verification, the coordinator applies Default dev integration, unless the assignment limits delivery. Read Merge readiness to check current CI and reviewer evidence using the repository's actual configuration. Serialize integrations that share a target, verify the landing, and update the coordination record. A capable child owns its commits, push, pull request and the review handling on it, and reports once the current head is clean; the coordinator decides and performs the merge, and the child never merges. Release and deployment still require the user. Delivery ownership and the fallback for a task that cannot write git metadata are in Operations contract.
Report verified, needs changes, or unverified, with concrete evidence, and distinguish implementation, merge, and deployment. Start a successor only after its required contracts/revisions are verified and available in its checkout and it belongs to the agreed project scope or explicit narrower assignment. This is the same rule in Run and Loop; a goal changes persistence, not scope.
Name what the work is doing in the vocabulary its contract already defines, rather than
in words invented for the report. Ordinary progress, waiting on input, a stop and a
request for verification are conditions the parent has to tell apart, and two contracts
supply the words for different questions. What the child's turn did is a
turn disposition: in_progress,
ready_for_review, blocked_needs_input, interrupted or failed. Where the
delivery stands is
the assignment state when a relay
holds it. Report them separately; a child blocked on a person has a turn that stopped
and a delivery that did not move, and one word cannot carry both. A condition neither
vocabulary names is reported as a blocker against the state that does apply, under
OPS-6.2.
After integration, apply Implementation Done before reporting or recording the issue complete. Read back the one delivery PR's actual merge, intended repository/branch and landing revision. For legacy multi-PR scope, verify the reconciled deliveries and their combined coverage instead. Retain existing accepted operational criteria and never infer completion from an automatic status alone.
Return corrections to the existing task
Apply the completion-follow-up rule in Integrations. Send an actionable packet to the existing responsible task without asking Jun to approve or relay routine in-scope corrections. Include the issue and criterion, reviewed revision, expected and observed behavior, reproducer/evidence, required outcome, and focused verification. For missing proof, request that verification without prescribing an unsupported code change.
Carry the restoration block with every correction. A running task has been working for a while, may have been compacted, and is being addressed by a coordinator whose context it cannot see, so the facts it needs to resume correctly are stated again rather than assumed to have survived. That is the same reason the first request named the workflow: naming it once, at creation, is not the same as it still being in force ten turns later.
Where a relay holds the assignment, the needs-changes verdict IS the correction: it opens the next execution generation and queues the revision request to the same registered child, carrying the superseded event, its digest, and the per-criterion findings. Record findings with notes, because a correction with no findings is one nobody can act on. Do not create a task, a second relationship, or a parallel message path to deliver it. Without a relay, send the packet as described above.
The restoration block rides inside that payload rather than beside it. The findings and their notes are what the relay actually delivers to the child, so that is where the block goes, and a verdict is not issued until it is there. Where the installed relay cannot carry it, that is a limitation recorded and reported on the assignment, and it is still not a reason to open the parallel path the sentence above forbids. Nor is there a supported way to send it again afterwards: the verdict does not resend. Record it as an undelivered correction and hand the decision to whoever owns the assignment, per codex-session-relay and the restoration block.
Refresh the task's identity, ownership, current turn, checkout, and prior correction receipts before sending. Reuse its agreed model, effort, workflow, permissions, and delivery scope. Of those the workflow is the one only the message can carry, because a transport transmits model and effort as settings and has no field for it. Route by what the task is actually doing: an idle task takes the ordinary message path, and a task whose turn is running is steered into that turn using its verified thread and active turn id. A transport that refuses a message to an active task is protecting its turn, and that is a reason to steer rather than a reason to wait for idle. If the turn changes between reading the state and sending, the send is refused: read the state again and reclassify instead of retrying. Send one correction by one route, never both. A timeout or an uncertain send requires reconciliation, never a duplicate writer or blind resend. Report a concrete access or ownership blocker when no supported path is available. Whether a tool exposes steering and whether the host supports it are established separately; a capability this bridge withholds is not a capability the host lacks.
Confirm the accepted turn, then inspect the returned revision and rerun the failed criterion and relevant regression checks. Continue within the same scope while the evidence supports a next correction; escalate a scope decision or a blocker that cannot be resolved under the assignment. Report actual progress without treating dispatch as repair completion. Keep requirements, issue state, merge, and deployment under their existing authorization.
Resume and handoff
On resume, read the coordination record and refresh its known task IDs before creating anything. Recover after uncertain delivery; do not duplicate a writer. Do not restart a stopped task merely to inspect it.
A resume this task publishes into an existing child carries the same restoration block a correction does, for the same reason: it is a message into a context this task cannot read. Two recoveries are easy to write as one event and are not. This coordinator recovering its own lost context is the paragraph above, done from the coordination record. A child recovering its own is that task's affair, handled by its own workflow from its own durable state; the coordinator supplies the pointers and the assignment facts it holds and does not reconstruct the child's plan on its behalf.
A final update gives task links/IDs, requested and verified settings, actual progress, review outcome, and the next actionable dependency. Use the host's created-task directive when required. State remaining capability gaps plainly. This skill does not install a recurring monitor: use the automation tools only when ongoing background monitoring is requested.