CM+ File Integration: XER / MSPDI / Excel / PDF
All imported files are untrusted input: enforce size limits, validate structure before processing, parse in constrained code paths, and never trust file extensions.
Primavera P6 (.XER)
- Tab-delimited text; tables start with
%T <name>, fields%F, rows%R. - Import these tables:
PROJ(project),PROJWBS(WBS),TASK(activities),TASKPRED(relations: FS/SS/FF/SF + lag),CALENDAR,TASKRSRC(resource/cost). - Skip bloat tables:
RISKTYPE,POBS(data cleansing per docs/วิเคราะห์ฯ §2). - Referential validation before commit: every TASK must reference an existing WBS row; every TASKPRED must reference two existing tasks; every task calendar must exist. Orphaned records → reject file with a row-level error report, not partial import.
- Percent-complete semantics differ by P6 type (duration/physical/units) — map explicitly; document the mapping in the import result.
MS Project (.MPP → MSPDI)
- Do NOT parse binary .MPP directly or via Office interop (unstable in cloud — docs/วิเคราะห์ฯ).
- Use MSPDI (Microsoft Project Data Interchange XML) via MPXJ.Net: tasks, WBS outline, resources, assignments, calendars (incl. exceptions), baselines, milestones.
- XML hardening: disable DTD/external entities (XXE), cap file size and node depth.
Excel (EPPlus)
- Import (weekly progress): protected structured template — locked layout, hidden
ActivityIdcolumn as the join key, data validation on % (0–100). On upload: validate every row, report all errors at once (row + reason), apply as one transaction. - Export: schedule + relations round-trip for external editing; escape any cell starting
with
=,+,-,@(formula injection); license EPPlus appropriately (commercial).
PDF export
- Executive reports: header with project info + data date, S-Curve chart, EVM table (SPI/CPI/EAC), progress photos grid by zone, Thai fonts embedded (IBM Plex Sans Thai).
Round-trip integrity (QA contract)
Import → export → re-import must be lossless for: WBS hierarchy + codes, activity dates and durations, relation types + lags, budget values. Golden-file tests compare against reference values produced by real P6/MSP (project risk #2, docs/2. — Critical severity).